Workshop for Work Packages 3
Kick-off Meetings for Work Packages 4 & 5

(25 - 29 May 2002)

Agenda

 

Tentative Agenda for Workshops 25-29 November

Nov. 25. : Steering committee meeting 4 and TIP meeting 3
Attendance: Steering committee members, TIP members

Time
Activity
Associated WP
     
0900 - 0915
Meet with coffee
0915 - 1215
TIP committee, incl. coffee/tea break
9
1215 - 1315
Lunch
1315 - 1700
Steering Committee meeting, incl. coffee/tea break
10

 

Nov. 26.: Work package 3 workshop
Attendance: participants in WP3, WP4 and WP5 are requested, open to all

Time
Activity
Associated WP
     
0900 - 0915
Meet with coffee
0915 - 0945
introduction of objective, requirements, use cases
3
0945 - 1015
coffee/tea break  
1015 - 1100
presentation of leading principles
3
1100 - 1130
demo prototyping
1130 - 1230
presentation on misc. topics
3
1230-1330
Lunch
1330-1530
Open Forum/discussion
3
1530-1600
Coffee/tea break
1600-1700
Discussion cont’d
3

 

Nov. 27.: Joint kick-off Work package 4 and 5
Attendance: WP4 and WP5 participants, representatives of WP2, WP3 and WP6

Time
Activity
Associated WP
     
0900 - 0915
Meet with coffee
0915 - 0945
introduction on WP 4 objective, plan
4 and 5 jointly
0945 - 1015
introduction on WP 5 objective, plan
4 and 5 jointly
1015 - 1045
coffee/tea break
1100 - 1130
discussion - identification of components to be designed by WP4 and WP5 (based on requirements analysis)
4 and 5 jointly
1130 - 1230
discussion - identification which components (within or outside project) may have potential impact on architecture / interface design
4 and 5 jointly
1230-1330
Lunch
1330-1500
discussion - allocation of functionality/component designs between WP 4 and WP 5
4 and 5 jointly
1500-1530
Coffee/tea break
1530-1700
development approach:
• similarities and differences between WP 4 and 5
• interaction between WP4 and WP5
• relations with WP6 (prototyping, level of detail)
• design methodology
4 and 5 jointly

 

Nov. 28.: Parallel session Work package 4 and 5
WP4 attendance: WP4 participants, representatives of WP3
WP5 attendance: WP5 participants, representatives of WP2

Time
Activity
Associated WP
     
0900 - 0915
Meet with coffee
0915 -1015
Task identification
• based on architecture identify issues and components to be worked upon
4
Task identification
• requirements review, allocate requirements to individual tools
• brainstorm on additional functionality of tools

5
1015 - 1045
coffee/tea break
1100 - 1230
working procedures
• identify how work is distributed (if desired allocate issues/components to various parties)
• determine design methodology
• discuss QA procedure
• define table of contents of design documents
4
working procedures
• allocate tools/components to various parties
• determine design methodology
• discuss QA procedure
• define table of contents of design documents
5
1230-1330
Lunch
1330-1500
produce relevant questions/points of interest to WP5
4
produce relevant questions/points of interest to WP4
5
1500-1530
Coffee/tea break
1530-1700
joint discussion on interrelated issues / points of interests
4 and 5 jointly

Nov. 29. Parallel session Work package 4 and 5
WP4 attendance: WP4 participants, representatives of WP3
WP5 attendance: WP5 participants, representatives of WP2

Time
Activity
Associated WP
     
0900 - 0915
Meet with coffee
0915 - 1015
• collective brainstorm on various issues identified
4
• Individual work on tools, to see if methodology is workable, gain some experience and obtain hands on clarity of what needs to be done
5
1015 - 1045
coffee/tea break
1100 - 1230
• collective brainstorm on various issues identified
4
• Individual work on tools cont’d
5
1230-1330
Lunch
4 and 5 jointly
1300-1400
Synchronise activities between WP 4 and WP 5
1400-1500
Complete planning
• Finalise detailed time planning for 2003
• distribution of tasks
• prepare action list
4 and 5 separately

 

 